The Facilities Master Plan for the San Elijo Campus looks to create a strong organization structure to unify the campus and which focuses on the renovation and modernization of existing facilities to provide flexible and interactive 21st century learning environments, transforming interior environments with technology upgrades, updated finishes, and furniture, fixtures, and equipment to promote collaborative learning, and expanding available tutoring and studying spaces throughout the campus.
Approved and planned projects are listed below. As additional projects are approved, scope defined, and budgets established, they will be added here.
View San Elijo Campus Project Fact Sheet.
Project | Status |
---|---|
Building 400 Science Labs Renovation | Design |
Building 900 Student Center Renovation | Design |
Building 100 Library Renovation | Construction |
Building 200 Fine Arts/Music Renovation | Construction |
Building 1100 New Student Services & Administration Building | Construction |
Building 300 Classrooms Renovation | Completed |
Building 500 Computer Lab Renovation | Completed |
Building 600 Modernization | Completed |
Swing Space/Temporary Housing | Ongoing |
Building 700 Renovation | Future |
Building 800 Renovation | Future |
Renovation of Central Campus Quad | Future |
Renovation of Mechanical and Electrical Utilities | Future |
New Monument Signage | Future |
CONSTRUCTION SCHEDULE KEY
- Spring: March 1 - May 31
- Summer: June 1 - August 31
- Fall: September 1 - November 30
- Winter: December 1 - February 28
CAMPUS PROJECT MANAGEMENT TEAM
- Campus Manager: Ed Dajani, Kitchell Capital Expenditures Managers (CEM)
- Project Manager: David Haddad, Kitchell CEM
- Project Manager: Anthony Hua, Kitchell CEM
- Project Engineers:Erin McGowan and Phan Uong, Kitchell CEM
Building 100 Library Renovation
Project Delivery Method: Design-Bid-Build
Phase: Construction
Project Budget: $5.8 million
Construction Duration: Winter 2020 - Summer 2021
Funding Source: Measure MM
SCOPE/SUMMARY
Building 100 serves as the library at the San Elijo campus, and will undergo a moderate renovation, allowing for the reconfiguration of existing computer labs into an expanded Tutoring Center.
The project will also include the upgrade of aging electrical systems, replacement of the aging heat pump, and a retiling of the roof. More than 14,000 square feet will be upgraded altogether.
PROJECT TEAM
- Architect: PBK Architecture
- General Contractor: Conant Construction
- Landscape Architect: PBK Architecture
- Mechanical, Electrical & Plumbing Engineer: P2S Engineering
Structural Engineer: Saiful Bouget Structural Engineers - Geotechnical Engineer: SMS Geotechnical Solutions
- Special Inspections & Materials Testing: TBD
- Inspector of Record: Construction Inspection Services
Building 200 Fine Arts/Music Renovation
Project Delivery Method: Design-Bid-Build
Phase: Completed
Project Budget: $4.3 million
Construction Duration: February - January 2021
Funding Source: Measure MM
SCOPE/SUMMARY
Building 200 provides classrooms for art, dance, and music, along with an outdoor amphitheater. The building underwent a full modernization, along with replacements of the mechanical, electrical and plumbing systems. The exterior ceramics yard was upgraded to an enclosed and air-conditioned space that is equipped with air cleaning safety systems to collect sawdust and glazing dust from art activities. New finishes, fixtures, furniture, and equipment provided throughout.
PROJECT TEAM
-
- Architect: SGPA Architecture
- General Contractor/Construction Manager: Straight Line General Contracting
- Mechanical/Electrical Engineering: Glumac
- Geotechnical Engineer: SMS Geotechnical Solutions
- Special Inspections & Materials Testing: MTGL
- Inspector of Record: Vital Inspection Services
Building 300 Classrooms Renovation



Project Delivery Method: Design-Bid-Build
Phase: Completed
Project Budget: $2.7 million
Construction Duration: January - August 2019
Funding Source: Measure MM
SCOPE/SUMMARY
The renovation of Building 300 - a 29,000 square feet general purpose classroom building - involved the modernization of eight classrooms, the tutoring center, and lab spaces. The building was completely overhauled with new mechanical, electrical, and plumbing systems, technology upgrades, and new classroom finishes, furniture, and fixtures. The project also included a full roof re-tiling, restroom and accessibility upgrades, the addition of a new custodial room, and a new intermediate distribution frame (IDF) room to support the upgrades in technology.
PROJECT TEAM
-
- Architect: Mosher Drew
- Structural Engineer: KPFF Consulting Engineers
- Mechanical & Plumbing Engineer: MA Engineers
- Electrical Engineer: Michael Wall Engineering, Inc.
- Fire Alarm: Michael Wall Engineering, Inc.
- Inspector of Record: Alliance Engineering
Building 400 Science Labs Renovation
Project Delivery Method: Design-Bid-Build
Phase: Design
Project Budget: $3.9 million
Construction Duration: Spring - Winter 2021
Funding Source: Measure MM
SCOPE/SUMMARY
Building 400, a science and computer lab building, will undergo a moderate renovation to convert the existing computer labs into an expanded Student Center/Library. Renovation of the classrooms and science labs will meet updated space standards. The project will also involve renovation of the building’s electrical systems, replacement of the heat pump, and the retiling of the roof.
PROJECT TEAM
Architect: HPI Architecture
General Contractor: TBD
Civil Engineer: Latitude 33 Planning and Engineering
Landscape Architect: KTUA
Mechanical, Electrical &Plumbing Engineer: P2S Engineering
Structural Engineers: MHP
Geotechnical Engineer: TBD
Special Inspections & Materials Testing: TBD
Inspector of Record: TBD
Building 500 Computer Lab Renovation


Project Delivery Method: Design-Bid-Build
Phase: Completed
Project Budget: $3.8 million
Construction Duration: July 2019 - January 2020
Funding Source: Measure MM
SCOPE/SUMMARY
Building 500 originally housed six classrooms, faculty offices, and the Language Resource Center. The renovation project provided for the reconfiguration of the spaces to provide two new computer labs, a technology-rich active learning classroom with movable seating and tables, and the modernization of all classrooms. Additionally, the building was re-roofed.
PROJECT TEAM
- Architect: Little Diversified
- General Contractor: Conan Construction
- Landscape Architect: Little Diversified
- Civil Engineer: Little Diversified
- Mechanical, Electrical & Plumbing Engineer: P2S Engineering
- Structural Engineer: KNA Structural Engineers
- Inspector of Record: Alliance Engineering
Building 600 Building Modernization


Project Delivery Method: Design-Bid-Build
Phase: Completed
Project Budget: $2.5 million
Construction Duration: July 2018 - January 2019
Funding Source: Measure MM
SCOPE/SUMMARY
Classroom Building 600 includes approximately 5,300 gross square feet of space, including classrooms for English, humanities, and social sciences classes. The project involved a full-building renovation, along with replacements of the mechanical, electrical, and plumbing systems, and replacement of some exterior building elements. Interior spaces were reprogrammed, and all classrooms updated with new interior walls and finishes and modern technologies.
PROJECT TEAM
- Architect: Architects Mosher Drew
- General Contractor: Conan Construction
- Electrical Engineer: Michael Wall Engineering
- Structural Engineer: KPFF Consulting Engineers
- Geotechnical Engineer: SMS Geotechnical Solutions
- Mechanical Engineer: MA Engineers
- Inspector of Record: Alliance Engineering
- Special Inspections: MTGL
Building 900 Student Center Renovation
Project Delivery Method: Design-Bid-Build
Phase: Design
Project Budget: $2.4 Million
Construction Duration: Spring - Winter 2021
Funding Source: Measure MM
SCOPE/SUMMARY
The B900 building is the Student Center of the San Elijo Campus and will be undergoing a partial renovation. The current bookstore and conference room functions will be moving to the new Student Services and Administration Building. This will allow for creation of more student-centered gathering spaces for clubs and student organizations, expansion of Health and Mental Counseling into more functional space, addition of gender-neutral restroom, and a mother’s lactation room.
PROJECT TEAM
- Architect: PBK Architecture
- General Contractor: TBD
- Mechanical, Electrical, and Plumbing Engineer: P2S Engineering
- Structural Engineer: Saiful Bouqet Structural Engineers
- Geotechnical Engineer: TBD
- Special Inspections & Materials Testing: TBD
- Inspector of Record: TBD
Building 1100 New Student Services & Administration Building
Phase: Construction
Project Budget: $13.9 million
Construction Duration: Summer 2019 - Spring 2021
Funding Source: Measure MM
SCOPE/SUMMARY
The Student Services and Administration Building will replace the existing Administration
building and consolidate key student services into a single location. the new 10,770
square feet facility will provide administrative offices and meeting spaces that will
improve the ability of staff to serve the student body, as well as gathering and socialization
spaces. Programs and services to be housed in the new building include Admission
& Records, Financial Aid, and Counseling. Offices for the campus administration will
also be included.
The new building is intended to provide a welcoming new gateway for the San Elijo campus. The design involves locating large portions of the building circulation to exterior covered spaces. These covered areas create several areas with seating and spaces for students to congregate, as well as additional ‘spill-out’ space for the building’s multipurpose room. The building is organized along a central circulation spine separate entrances for students; staff and faculty are located at each end. The main building lobby is located at the south-west corner of the plan, with commanding views out to the lagoon; as well as providing the iconic ‘lighthouse’ for the campus from Manchester Street.
The building’s façade will complement the exposed bluff faces surrounding the campus, using split-face concrete blocks to mimic the texture of the bluffs. An art walk will be located in the building arcade, featuring student murals on interchangeable wall mounted panels.
Additional sustainable design strategies include:
- Passive sun shading/roof overhang
- Abundance of natural light inside the building via storefronts and skylights
- North-south solar orientation for the building and circulation axis
An ADA-compliant student drop-off will also be installed at the entry to the San Elijo Campus as part of this project.
PROJECT TEAM
- Architect/Civil Engineer: Little Architecture
- General Contractor/Construction Manager: Barnhart Reese Construction
- Landscape Architect: LandLAB Environmental Design
- Mechanical/Electrical Engineer: P2S Engineering, Inc.
- Structural Engineer: KNA Structural Engineers
- Environmental Engineer: Dudek
- Geotechnical Engineer: SMS Geotechnical Solutions
- Inspector of Record: Consulting Inspection Services
Swing Space/Temporary Housing
Phase: Ongoing
Project Budget: $2.9 million
Construction Duration: February 2018 - January 2019
Funding Source: Measure MM
SCOPE/SUMMARY
The initial phase of temporary portables included three classrooms, office space, and a restroom. Second phase provided two additional classrooms.
PROJECT TEAM
- Architect: MJK Architecture
- Landscape Architect: The Lightfoot Planning Group
- Construction Manager/General Contractor: Various
- Civil Engineer: Spear and Associates
- Electrical Engineer: Johnson Consulting Engineers